I have a very simple setup that I am using to test the Master and Resource Pool functionality. One master with two very small inserted subprojects that are sharer files to a resource pool. When using the master project to create visual reports I am getting unexpected results for my resource work hours. Usually the visual report for a given resource shows a multiple of 4 or 9 for the working hours that are shown in the masters resource graph on the view bar. Example: Resource A for the month of October shows 352 hours in the master resource graph view, which is the correct number for the combined hours of resource A for the two subprojects. The visual report shows 1,408 hours, instead of 352 hours. I have had this working correctly before, but more times than not I am seeing multiples of 4 for the working hours.